5.3.4 Abort an executing job

A job which is currently in the K queue (Submitted for execution) or the L queue (Execution started) can be aborted either through a SCHEDULE


 
 
Schedule> catque k,l 
 
Scheduling queue K: Submitted for execution 
 
 
Scheduling queue L: Execution started 
 
119. /demo/d/a1 (1559) Execution queue entry 695 
 
 
 

Then enter either of the following commands:


 
 
Schedule> chque -entry=119 -abort 
 
$ delete -entry=695 
 
 
 

This will cause the job to terminate with a FAILURE result status. Since job A1 was configured for both BROADCAST and MAIL notification upon a FAILURE result, within a few seconds the following messages appear on the screen:


 
 
 
Reply received on DWS from user SYSTEM at DWS Batch 09:59:48 
/demo/d/a1 - Job failed 
 
New mail on node DWS from CLUSTR::SYSTEM "Job scheduler" 
 
 
 
 
 
 

The mail message appears as follows:


 
#1 13-DEC-1996 09:59:57.22 NEWMAIL 
From: CLUSTR::SYSTEM "Job scheduler" 
To: JDOE 
 
CC: 
Subj: /demo/d/a1 - Job failed 
 
------------------------------------------------------------------ 
 
S C H E D U L E Event Notification 
/demo/d/a1 - Job failed 
 
 
Desription: 
 
Job /demo/d/a1 
Startup check before database update 
 
 
Current time 13-DEC-1996 09:59:49.90 
Set id 1560 
Set tag 
Set parameter 
Scheduling entry 0 
 
 
Started 13-DEC-1996 09:59:10.43 
Finished 13-DEC-1996 09:59:34.31 
Status %X00048084 
%JBC-F-JOBABORT, job aborted during execution 
------------------------------------------------------------------ 
 
Job A1 has failed. Correct the cause of the failure and manually 
resubmit job A1. 
 

5.4 Review events of job execution

The events that occurred during the execution of the jobs are saved in a history database. These events can be reviewed by displaying a simple listing on the screen or by generating a formated report.

5.4.1 Simple listing

To output a simple listing on the screen of job completion events from the last 24 hours, use the following commands:


 
 
 
 
Schedule> cathist /demo/d/* -queue=r -from=now-24 -to=now 
 
/demo/d/a1 
December 5, 1996, 12:39 R Msg comp 
 
/demo/d/a2 
December 5, 1996, 12:41 R Msg comp 
 
/demo/d/a3 
December 5, 1996, 12:41 R Msg comp 
 
/demo/d/b1 
December 5, 1996, 12:43 R Msg comp 
 
/DEMO/D/B21 
December 5, 1996, 12:44 R Msg comp 
 
/demo/d/b22 
December 5, 1996, 12:45 R Msg comp 
 
/demo/d/b23 
December 5, 1996, 12:45 R Msg comp 
 
/demo/d/b24 
December 5, 1996, 12:46 R Msg comp 
 
/demo/d/f 
December 5, 1996, 12:48 R Msg comp 
 
/demo/d/g 
December 5, 1996, 12:47 R Msg comp 
 
/demo/d/h 
December 5, 1996, 12:49 R Msg comp 
 
/demo/d/i 
December 5, 1996, 12:50 R Msg comp 
 
Schedule> cathist  /demo/d/b21 -queue=r -from=now-24 -to=now -full 
 
/demo/d/b21 
 
December 5, 1996, 12:44 R Msg comp 655 /demo/d/b21 (1484) 
step:0 tag:"" param:"" 
node:DWS queue:DWS$BATCH entry:322 
strt:December 5, 1996, 12:42 Sts:00030001 CPU:5 Elps:99 IO:252 Flts:1821 
Ppg:4675 
 
 
 

5.4.2 Report writer

To generate a formatted report of selected events from the last 24 hours, use the following command:


 
 
Schedule> report schh_user_allevent_all_80 -submit 
 
Output: 
Directory: /demo/d/ 
 
 
Job: * 
Minimum set id: 1 
Maximum set id: 99999 
From log date: NOW-24 
To log date: NOW 
Queue list: E*,R*,U* 
Job SCHH_USER_ALLEVENT_ALL_80 (queue SYS$BATCH, entry 561) 
started on SYS$BATCH 
 

See the chapter on report generation for a complete description of what reports are available and what information to supply in the command.

This will produce a report listing with the default file name of SCHH_USER_ALLEVENT_ALL_80.LIS with the following contents:


ISE, INC. ISE, Inc. SCHEDULE V4.0 
December 5, 1996, 13:49 Summary of events Page 1 
selected by all settings 
(SCHH_USER_ALLEVENT_ALL_80) 
 
Log date Event Job name Set id Cpu time Io count 
 
 
12- 5-96 12:39 U Msg started /demo/d/a1 1,484 4.25 218 
12- 5-96 12:39 R Msg comp /demo/d/a1 1,484 5.04 276 
12- 5-96 12:40 U Msg started /demo/d/a2 1,484 4.37 196 
12- 5-96 12:41 R Msg comp /demo/d/a2 1,484 5.19 254 
12- 5-96 12:41 U Msg started /demo/d/a3 1,484 
12- 5-96 12:41 R Msg comp /demo/d/a3 1,484 
12- 5-96 12:43 U Msg started /demo/d/b1 1,484 4.70 189 
12- 5-96 12:43 U Msg started /demo/d/b21 1,484 4.72 190 
12- 5-96 12:43 R Msg comp /demo/d/b1 1,484 5.54 250 
12- 5-96 12:44 U Msg started /demo/d/b22 1,484 4.69 192 
12- 5-96 12:44 R Msg comp /demo/d/b21 1,484 5.61 252 
12- 5-96 12:45 U Msg started /demo/d/b23 1,484 4.54 188 
12- 5-96 12:45 R Msg comp /demo/d/b22 1,484 5.58 253 
12- 5-96 12:45 R Msg comp /demo/d/b23 1,484 5.38 251 
12- 5-96 12:46 U Msg started /demo/d/b24 1,484 4.42 196 
12- 5-96 12:46 R Msg comp /demo/d/b24 1,484 5.22 259 
12- 5-96 12:47 U Msg started /demo/d/g 1,484 4.46 196 
12- 5-96 12:47 U Msg started /DEMO/D/F 1,484 4.45 194 
12- 5-96 12:47 R Msg comp /demo/d/g 1,484 5.24 258 
12- 5-96 12:47 E Wtfr prereqs /demo/d/h 1,484 
12- 5-96 12:48 R Msg comp /demo/d/f 1,484 5.23 256 
12- 5-96 12:48 U Msg started /demo/d/h 1,484 4.47 216 
12- 5-96 12:49 R Msg comp /demo/d/h 1,484 5.22 282 
12- 5-96 12:49 U Msg started /demo/d/i 1,484 4.56 195 
12- 5-96 12:50 R Msg comp /demo/d/i 1,484 5.35 258 
 
 
 


Part 3
Line command reference

This part of the manual is a command reference for all aspects of the SCHEDULE program.


Chapter 6
CALENDAR data operations

In SCHEDULE number of calendars can be defined. Some can be setup to be used system wide. Others just to be used by jobs inside a particular directory. The main purpose of a calendar definition is to assist in determining when to automatically reschedule a job.

For example you have a job that is to run every 3 days. Along with this interval you define a calendar which describes which days are allowed. This job may not be allowed to run on weekends. These two bits of information are used to control this automatic rescheduling process.

Calendar data is managed and maintained using the following commands.
Command Description
cpcal copy a calendar definition
mkcal create a new calendar definition
rmcal delete a calendar definition
lscal list known calendar definitions
chcal modify a calendar definition
mvcal rename a calendar definition
morecal type out the days in the calendar

When a calendar is mentioned in a job definition it is found by the following method:

Once a calendar has been found the flag settings are examined to see if one of the HOLIDAY flags is set. If so, a HOLIDAY calendar is located using the same three steps listed above. Once the holiday calendar has been found it is merged into the selected calendar to form the final calendar that will be used for rescheduling.


cpcal

Copy a calendar file.

The cpcal command will copy a calendar definition into another named calendar definition.


General Format

cpcal [-options] from_name to_name

Alternate

copy -calendar [-options] from_name to_name

option summary

-[no]log
-[no]confirm
-node = node_name

Examples

#1

 
 
Schedule> cpcal /dst/weekdays /sdey/wkdays -log 
 
 copied /dst/weekdays to /sdey/wkdays 
 
 
      


Options

-confirm

-noconfirm

CONFIRM requests that the user be prompted prior to any operation to verify that the selected entry is the correct one.

-node=target_node

The hostname option specifies what hostname (either local or remote) you want the operation performed on. -hostname may be substituted for -node.

-log

-nolog

The LOG qualifier causes each completed operation to issue a note to the user.

chcal

Modify a calendar definition.

The chcal command will change any of the fields that make up a calendar definition.


General Format

chcal [-option = value] calendar_name

Alternate

modify -calendar [-option = value] calendar_name

option summary

applicable to the calendar header entry:

-owner = uic
-protection = (ugo+/-rwx)
-comment = "any text string"
-[no]workdays [= noholiday, noweekend]
-flags = noholiday_runs, noweekend_runs, skip, slide
-fiscal = starting month

applicable to the calendar month detail record

-date = date to change
-mark = letter or letters
-[no]run
-standard_date

general qualifiers:

-log
-confirm
-node = target node


Examples

#1

 
 
 
 Schedule> chcal /mlevy/fun_days -fiscal=july -log 
 modified  /mlevy/fun_days  
 
 
      


Options

-comment="any text string"

The COMMENT option is any useful description that you may want to add. This is an 80 character option.

-confirm

-noconfirm

CONFIRM requests that the user be prompted prior to any operation to verify that the selected entry is the correct one.

-date=date to change

The DATE option is used to change a date on a calendar. The presence of the DATE option selects a detail record modification.

-node=target_node

The hostname option specifies what hostname (either local or remote) you want the operation performed on. -hostname may be substituted for -node.

-fiscal=starting month

The FISCAL option specifies which month is to begin the fiscal year. The default setting is January. The month may be entered as a number (1-12) or as text (e.g. "June").

-flags=noholiday_runs, noweekend_runs, skip, slide

The FLAGS option allows the user to specify dates on which a job is to run. The various flags are:
Flag Description
NOHOLIDAY_RUNS No jobs will run on a holiday
NOWEEKEND_RUNS No jobs will run on a weekend
SKIP Skip runs on disallowed days
SLIDE Slide run forward on disallowed days

Whenever multiple flags are used, they must be enclosed in parentheses.

-log

-nolog

The LOG qualifier causes each completed operation to issue a note to the user.

-mark="markings"

The MARK option is used to mark certain days on a calendar.

-owner=[UID,GID]

The OWNER option specifies the owner user id and group id code for the calendar.

-protection:[who]+permission

-protection:[who]-permission

The PROTECTION qualifier modifies the read, write and execute permissions of specified calendars.
who specifies whether permissions are being defined for user(u), group(g) or all others(o).
permission specifies the permissions being defined. Read permission(r) allows reading. Write permission (w) allows the ability to write out a new version. Execute permission(x) allows execution of jobs and calendars, search of directories.

-run

-norun

The NORUN option s marks the specified day as one on which no runs are allowed.

-standard_date

The STANDARD_DATE option indicates that the date provided with the -date option is a standard date. This is useful when modifying a particular date of a workday calendar. Only the work days of such a calendar have numbers. To mark a specific day using a standard date (i.e. the date from a wall calendar) this option must be provided.

-workdays[=noholiday(d), noweekend(d)]

-noworkdays

The WORKDAYS option specifies which days a job will not run. The default settings are NOHOLIDAY and NOWEEKEND. To change a day on a WORKDAYS calendar that is not included in the defined workdays use the STANDARD_DATE option . Either noholiday, noweekend or both may be used.

lscal

Display on-line information.

The lscal command will display all or just selected portions of the calendar database.


General Format

lscal [-options] calendar_name

Alternate

directory -calendar [-options] calendar_name

option summary

-check
-column=number
-comment
-node = node_name
-fiscal
-flags
-full
-noheading
-notrailing
-out
-owner
-protection
-env=[prefix_string,format]
-template=/schedule_library/template_db.schedule
-workdays

Examples

#1

 
 
 
 Schedule> lscal * -full 
 
 
 
 
 


 
  
 
  
 /vlirette/specialdays 
     Comment                   = 
     Owner                     = [0,0] 
     Protection                = ugo+/-rwx  
     Workdays                  = 
     Flags                     = 
     Fiscal                    = 0 
 /vlirette/test_calendar 
     Comment                   = test calendar comment 
     Owner                     = [MRYAN] 
     Protection                = -rwxrw---- 
     Workdays                  = NoWeekend 
     Flags                     = NoHoliday_Runs 
     Fiscal                    = 2 
 
 /vlirette/vacation 
     Comment                   = 
     Owner                     = [SFRANCES] 
     Protection                = -rwxrw---- 
     Workdays                  = 
     Flags                     = 
     Fiscal                    = 0 
 /vlirette/weekdays 
     Comment                   = test 
            Owner                     = [0,0] 
            Protection                = -rwxrw---- 
     Workdays                  = 
     Flags                     = 
     Fiscal                    = 0 
 /vlirette/workdays 
     Comment                   = 
     Owner                     = [VLIRETTE] 
     Protection                = -rwxrw---- 
     Workdays                  = NoHoliday,NoWeekend 
     Flags                     = NoWeekend_Runs 
     Fiscal                    = 1 


Options

-check

Workgroup Jobs Only. The CHECK option displays the designated object's status on the nodes in the current workgroup. Any differences are displayed as:


 
 
 
  
node_name: different 
 

Adding the -log qualifier displays the specific differences between the object(s) on specific nodes. Ex:


 
\least_busy_4\job_job1.hdr 
    CWG: okay 
    DWG: different 
                Prv_Owner (215)= /0xc000000e/ 
                    Owner (015)= /0xc000000d/ 
    AWG: okay 
 

-columns=number

The COLUMNS option specifies how many columns to use when listing just the item name. The default is four columns.

-comment

The COMMENT option displays any useful description that you may have added.

-node=target_node

The hostname option specifies what hostname (either local or remote) you want the operation performed on. -hostname may be substituted for -node.

-fiscal

The FISCAL option displays which month is to begin the fiscal year.

-flags

The FLAGS option displays what special features are enabled. The various flags are:
Flag Description
NOHOLIDAY_RUNS No jobs will run on a holiday
NOWEEKEND_RUNS No jobs will run on a weekend

-full

The FULL option requests a display of all control information available on a calendar.

-noheading

The NOHEADING removes the heading information from the directory listing.

-notrailing

The NOTRAILING removes the trailing information from the directory listing.

-owner

The OWNER option displays the owner UIC code for the job.

-output=output_file

The OUTPUT option sends all output to a text file. Output can be printed or displayed as needed.

-protection

The PROTECTION qualifier displays the read, write and execute permissions of specified calendars.
who specifies whether permissions are being displayed for user(u), group(g) or all others(o).
permission specifies the permissions being displayed. Read permission(r) allows reading. Write permission (w) allows the ability to write out a new version. Execute permission(x) allows execution of jobs and calendars, search of directories.

-env[=prefix_string] or [=(prefix_string,format)]

The environmental variable option requests that all calendar information be output to a file containing a list of enviroment variables. Every field in the control record is listed in the file as an environment variable. The environment variable name is constructed by prefixing the field name with the provide string. If none is provided a default value of SM is used.

The format defines the way that environmental variables are output. The default output specification is: "$export %s=\" %s\" "" (ksh), "$setenv %s=\" %s\" "" (csh) which produces the following format style.


 
   SM_FLAGS = "Slide_over_disallowed" 
 

Alternate output styles may be created by changing the format field.

-template=/schedule_library/template_db.schedule

The template option formats the directory output as it is defined in the template file /schedule_library/template_db.schedule . This output can be used for a variety of reasons and can be output to a file using the OUTPUT option . The supplied template file extracts all database information into a format suitable for insertion if desired.

-workdays

The WORKDAYS option displays which days a job is to run.